Quoddy Bay LNG Project Timeline
December 2005:
Pre-filing application completed with FERC
March - May 2006:
Open houses &
scoping sessions
with public
June 2006:
Draft Resource
Reports 1-13 are filed with FERC
September 2006:
Public job information fair
Novermber 2006:
Formal application acceptance from FERC. All other permit applications to follow shortly
December 15, 2006
Submittal of formal application to the FERC
June 2007
Submittal of NRPA and SLOD Applications to the Maine DEP
August 2007
BEP assumed jurisdiction of Quoddy Bay DEP application.
August 31, 2007
Intervener deadline for Quoddy Bay DEP application.
4Q 2008
All permits in place and construction begins
2011
Initial operations begin
2012
Fully operational